Kovanlık temporary substation switchyard
Kovanlık Temporary Substation and Line

Project information
- Client
- Çelikler Elektrik Üretim
- Contract role
- Main contractor
- Location
- Ordu
- Period
- 2014
- Voltage
- 154 kV
- Status
- Completed
- Business area
- Transmission
Scope of work
- Kovanlık temporary substation — built in 105 days
- 32 km double-circuit 1272 MCM transmission line — built in 180 days